UniPhi 17 is Live!

With our first round of clients upgraded over the weekend, UniPhi17 is now a production release! 

This new version has two main aspects, a complete re-write of our contracts module and the implementation of embedded charts throughout the application. Why were these two elements our investment focus? 

Contracts module 


The contracts module is the fourth most intensive data capture area of UniPhi, after timesheets, issues and  documents. What's more the data is numbers heavy as it is used to track the adjusted contract value and progress invoicing across all purchases within a business or for a program of works. Feedback from clients was that while it was a lifesaver in terms of tracking all the adjustments that need to be administered to an original contract, data entry was slow and clunky. So we decided we'd respond with a focus on quicker data entry, easier re-formatting and the ability to build and manage larger and larger contract values.

Additional features for contracts while we're at it 

Earned Value

As we were investing in this module, we decided some new features were in order as well. For a while now we're been supporting clients track earned value at a project level but our engineering clients wanted more. They battle to track performance against deliverables during design, building complex spreadsheets that are hard to maintain with actual data in an attempt to do so. Again, we felt responsible for delivering something more and so, we introduced earned values for contract deliverables. Three new screens were essential for supporting this: An earned value screen to measure progress via a stage gate methodology, comment threads against contract deliverables to validate the earned value claim and an effort schedule that provides a baseline at the WBS level for planned performance. 

 
Earned value webinar

Charts - In 2018 we released as part of UniPhi 14 a direct integration with Power BI and an embedded Power BI product that allows you to publish your own charts within the application, however, there are two issues with this: You need to have internal capability to build the dashboards and you can only view them in the embedded dashboard page. We wanted to support all our clients plus be able to give instant visual feedback to our users when they change budgets, add issues or risks, commit contracts and submit timesheets. These charts have generated significant interest from our user base and we plan to leverage this concept with more and more charts supported by drag and drop selection for users to get the visual that means most to them right where they need it.


 

The full webinar series for UniPhi 17 is in a playlist on YouTube.

So, if any of this has piqued your interest, give us a call or register for a demo. We'd love to show you our biggest and best release in years.

 


UniPhi 17 - New scheduling sub module for cash flow and effort

UniPhi 17 has split out the phasing of a contracts deliverables into two. In prior versions, a user could cash flow a contract by scheduling the deliverables and then using linear monthly phasing across those dates to drive when the forecast of when invoices will be raised. This then consolidates across the portfolio of projects to generate a corporate cash flow profile that can be sliced into states, sectors or any other portfolio subset imaginable.

UniPhi 17 expands this functionality considerably by adding an additional "effort" phasing screen and expanding the phasing algorithms to include other linear methods (i.e. quarterly, half year and yearly) as well as a standard "s" curve for main building contracts.

New effort view for contract schedule


The effort screen is only available for revenue contracts and only when you have developed your contract values from a bottom up estimate of task and assignment. By assigning resources to tasks and phasing out the effort, the end user instantly has a baseline earned value profile for that project. Note we can then cash flow at a higher level for milestone claims and as these don't represent the effort profile, both are catered for.

Feedback to the end user is presented in the form of total contract hours estimated, current actual hours and forecast remaining. Updated schedules push out the remaining hours only.

A baseline function enables users to compare current forecast to the original profile and also is the trigger for the budgeted cost of work scheduled when assessing earned value on the deliverable.

Finally, the hours phased in the contract screen push to the resource planning module to provide a bottom up cumulative effort profile for each person on the project, enabling a virtuous circle from proposal estimate to project management to timesheets to invoicing to cash flow to profitability to resource planning and back to estimating at completion costs.

This to our knowledge, is the only system in the world capable of doing this.